This is part of the capacity redistribution of the Sungai Selangor Phase 3 Water Treatment works. Originally water from the Bukit Jelutong Reservoir flows by gravity to the HICOM Reservoir. Due to projected increase in demand, this water will instead be pumped from the supply reservoir.
SKE Alliance Sdn Bhd undertook the bulk of the works, which included the following:
Civil works:
Mechanical & electrical works:
The project was completed on time and successfully commissioned. The defects liability period has since lapsed with no major issues.